Morris-Shea used a Fundex F3500 drill rig to install more than 200 continuous flight auger (CFA) piles as a deep foundation for a Raleigh, NC multi-story office tower. The CFA foundation was ideal for the soil conditions at the jobsite. The 36 inch diameter piles were installed in lengths up to 90 feet at an average of 12 per day.